PMP — People and Process flashcards

10 of 80 cards free to study here · 2 topics · the whole deck is built into Willys

Team leadership, conflict, servant leadership, emotional intelligence and stakeholders, then integration and change control, scope, critical path, earned value, quality, risk responses, procurement and communications.

Learn deck · part of PMI Project Management Professional (PMP) · written against: PMP Examination Content Outline (People, Process, Business Environment; predictive, agile and hybrid). Updated 2026-10-10.

Study the free sample

10 cards from the deck as they are. Flip, rate yourself, filter by topic; your progress stays in this browser.

The 10 sample cards as a list
  1. A team member who has always been reliable has missed three deadlines in a row. What should the project manager do FIRST?
    Talk with the team member privately to understand what is going on before deciding anything — the cause may be workload, unclear priorities or a personal issue.

    Watch out: escalating to the functional manager or reassigning the work comes later, if at all.
    People › Team Leadership
  2. In order, what are the five stages of Tuckman's team development model?
    Forming, storming, norming, performing, adjourning. Teams can slip back a stage when membership or circumstances change.
    People › Team Leadership
  3. Two weeks after kickoff, team members are arguing about who owns what and how work should be done. Which stage is this, and how should the project manager respond?
    Storming. The project manager should coach and facilitate — clarify roles, help the team agree working norms, and let disagreements surface constructively rather than suppressing them.
    People › Team Leadership
  4. What does a team charter usually contain, and who should write it?
    The team's values, ground rules and working agreements, including how decisions are made, how conflict is handled and how members communicate. The team writes it together, so members own it.
    People › Team Leadership
  5. A keen new hire has very little experience with the project's technology. Under situational leadership, which style fits best?
    A directing (telling) style — clear instructions and close guidance, shifting toward coaching, supporting and finally delegating as competence grows.
    People › Team Leadership
  6. What does the project charter do, and who issues it?
    The project charter officially authorizes the project and empowers the project manager to use the organization's resources on it. It comes from the sponsor or another initiator outside the project team.
    Process › Integration and Change Control
  7. A customer asks a developer directly to add a field to a report — just a small change — and the developer agrees. What should the project manager do?
    Stop the informal change and route it through change control: assess the impact on scope, schedule, cost and quality, and submit a change request for a decision.

    Watch out: small unapproved additions are how scope creep starts.
    Process › Integration and Change Control
  8. After a change request is raised in a predictive project, what is the usual order of steps?
    Assess the impact, identify options, submit it to the change control board (or other change authority) for a decision, then, if approved, update the plans and baselines, communicate the decision and implement it.
    Process › Integration and Change Control
  9. How does an issue log differ from a risk register?
    The issue log tracks problems that have already happened and need resolving; the risk register tracks uncertain future events that might happen.
    Process › Integration and Change Control
  10. When should lessons learned be captured on a project?
    Throughout the project, recorded as they arise and applied as the project goes, not only at closure.
    Process › Integration and Change Control

Unlock the whole deck

You are studying a free 10-card sample. All 80 cards of PMP — People and Process, the other 2 PMI Project Management Professional (PMP) decks, and spaced-repetition scheduling are built into Willys. 14-day free trial, then $14.99 a year.

In Willys, tap Exam Library at the top of your Decks (or Browse Exam Library… under the + button), find the exam on its shelf or by search, tick it and tap Add.

More PMI Project Management Professional (PMP) decks

← All PMI Project Management Professional (PMP) decks, with the study guide and topic outline.

About these cards

Review status: Second-reader reviewed, with corrections applied.

Checked against:

  • PMI PMP Examination Content Outline (2026 edition, for exams from July 2026) — topic outline only; no text copied
  • A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Eighth Edition (PMI, 2025) — PMI's public errata sheet (second printing) and table of contents used to check the conflict-technique, Validate Scope, charter and change-control cards; no text copied
  • NIST/SEMATECH e-Handbook of Statistical Methods, section 6.3.2 (U.S. government work) — used to check the control-chart run rules; no text copied

These are independent study notes written for Willys. They are not official exam material, may contain mistakes, and are no substitute for your course, your teacher or the exam owner's own publications. Found an error? Tell us — corrections ship as a new version of the deck.

PMP® and PMI® are registered marks of the Project Management Institute, Inc., which is not affiliated with and does not endorse this product.

Use of these pages is covered by our Terms of Use.